PITER J. BONILLA D.

Civil Engineer | Senior Project Controls & Quantity Surveyor | Infrastructure & Power Generation

Permanent Resident (Green Card) · No Sponsorship Required · Available Immediately · Greensboro, NC 27406
CODIA #17378 · PE License Dominican Republic (Active)
$2B+EPC Project Value
25+Years EPC Megaprojects
12.44kmTBM Alignment Control
75%Automation via Proprietary Tools
133Portfolio Documents

Professional Summary

Civil Engineer and Project Controls Specialist with 25+ years on large-scale power generation and infrastructure projects ($300M–$900M+) — hydroelectric dams, underground powerhouses, TBM tunnels, and high-voltage transmission. Delivered $2B+ in EPC project controls support with direct EPC contractor interface across field progress tracking, change order evaluation, and schedule integration. Recently relocated to Greensboro, NC to be near family — permanent resident with long-term commitment to the Triad market.

Career Evolution

2004–2011

Field Technical Expert
Advanced surveying, geometric design, quantity take-off on hydroelectric megaprojects. TBM alignment control, geodetic networks, underground powerhouse operations.

2011–2021

Systems Architect
Development and deployment of Visual CRP, AC&P, SALT and ICOD across $500M+ EPC projects. VBA-AutoCAD automation, document control, payment certification management.

2022–Present

Independent Consultant
Project controls consulting for Santiago Monorail ($1B+) and Soco-Yabacao ($863M). Technical ex-ante analysis. Visual CRP deployment for Guayubín Dam.

Project Lifecycle Impact

+85%Design
+95%Controls
+90%Evaluation

Quantified Results

75%Time ↓
$1.6MSavings
100%Audit ✓

"The implementation of Visual CRP transformed our operational document control. The hybrid approach delivered an estimated $1.6M in savings with complete traceability and highest honors in audit evaluations."

— Engineering Manager, Montegrande Dam Project

"The ex-ante evaluation methodology presented by Engineer Bonilla establishes a new standard for technical analysis in the design phase. It stands out for its capacity to integrate analysis of existing studies, comparative evaluation of international challenges, and rigorous study of applicable technologies, articulated through advanced technical-financial modeling."

— Ing. Carlos Sully Bonnelly Ginebra, PhD | International Consultant in PPP and Transport Economics | Faculty

Professional Experience

2022 – Present

Independent Consultant — Engineering Systems & Project Controls

Independent Practice · Dominican Republic / Remote / U.S.
  • Proprietary Systems: Developed and commercially deployed 4 proprietary engineering systems (Visual CRP, AC&P, SALT, ICOD) — applied across $2B+ combined project value.
  • Project Controls Consulting: Provided project controls and feasibility analysis for Santiago Monorail ($1B+, 2023–2024) and Soco-Yabacao Water Transfer System ($863M, 2025).
  • Visual CRP Deployment: Adapted and implemented Visual CRP for Guayubín Dam (2023) — 1,183 documents registered, 9 concurrent design firms managed.
  • U.S. Machine Control (2013–2015): Produced 3D terrain models for U.S.-based surveying firm — direct exposure to U.S. project documentation standards (Trimble/Topcon DTM workflow).
  • Technical Analysis: Independent financial analysis of Santo Domingo Metro Line 3 — quantified $2.3B operational funding gap using Newton-Raphson IRR methodology with 123,456 Monte Carlo iterations.
Visual CRPProject ControlsFeasibility AnalysisVBA Automation
Feb 2018 – Dec 2021

Surveying & Project Controls Manager | Technical Documentation Manager

Andrade Gutiérrez S.A. — Montegrande Dam Project ($500M+) · Dominican Republic
  • Quantity Surveying & Payment Certification: Resolved a critical impasse between the project's quantity department and client on earthwork volumes — 12M m³ excavation, 5M m³ backfill, 230,000 m³ concrete, 39,000 m³ asphalt core, 36,500 m³ underground tunnel. Delivered independent earthwork evaluation that unblocked the certification process.
  • Field Progress Tracking: Executed biweekly drone photogrammetry campaigns (Pix4D) over 12M m³ active excavation zone — correlated volumetric progress with construction schedule milestones for owner reporting and EPC contractor schedule validation.
  • Geotechnical Program: Supervised 1,300m borehole investigation across 6 structural zones — processed 104 Lugeon/Lefranc permeability tests, administered $289K subcontract with monthly quantity certifications.
  • LiDAR Automation (ICOD): Developed Excel VBA–AutoCAD API system in 2 weeks to automate tunnel cross-section generation from LiDAR data — 4,000+ pts/section, 2,800 sections auto-generated, 75% drafting time reduction. No commercial tool could handle the complexity.
  • Engineering Document Control: Deployed Visual CRP managing 15,000+ records across 4,000+ documents — 60+ daily users, validated by external auditors alongside Citadon/Construmanager/Procore, 100% audit compliance, $1.6M+ verified savings vs. commercial licensing.
Quantity SurveyingPix4DLiDARVisual CRPEPC Interface
Feb 2006 – Jul 2011

Survey & Topography Manager

Odebrecht (Norberto Odebrecht S.A.) — Palomino Hydropower Project ($400M+) · Dominican Republic
  • Underground Construction — TBM Operations: Led surveying operations for Dominican Republic's largest underground infrastructure project: 12.44km TBM double-shield tunnel (Herrenknecht/VMT SLS-HR guidance system), underground powerhouse with 11 interconnected tunnels, 400m-deep surge shaft, 60m CCR dam, and 19km transmission line — team of up to 80 personnel.
  • Field Quantity Certification ($708K Contract): Delivered Phase I roadway Pay Application No. 7: 95,273 m³ common excavation, 11,299 m³ dense excavation, 51,109 m³ material transport, 4,803 m² slope revegetation — verified per progress measurement protocol with CDEEE.
  • Change Order Evaluation: Evaluated and tracked change orders for access road geometry modifications — coordinated with on-site specialized designers, maintained alignment log against approved baseline design throughout construction.
  • Access Road Engineering: Developed geometric designs and drainage solutions (AASHTO 1993) for powerhouse, TBM portal, and surge shaft access routes — culvert sizing Ø30" to Ø72", crown ditches, retaining structures.
  • Geodetic Control & TBM Alignment: Managed topographic control network for full 12.44km TBM drive using SALT proprietary adjustment system — maintained alignment within specification throughout 20-month excavation (9,531 rings installed, completion March 2011).
TBM AlignmentQTO / Pay CertsChange OrdersAASHTO 1993SALT System80-person team
Aug 2011 – Jan 2012

Road Projects — Engineering Lead

Odebrecht — Bávaro-Miches & Ocoa-Piedra Blanca Road Studies · Dominican Republic
  • Led technical oversight of design consultant for two simultaneous road projects: Bávaro-Miches-Samaná Regional Highway (108km, V=80km/h) and Ocoa-Piedra Blanca Highway (mountain terrain). Identified critical geodetic error in a 4-year-old LiDAR study — traveled to Peru to demonstrate the error to the original subcontractor, resulting in full reprocessing at no cost (EGM2008 geoid vs. local geoid standard).
Road DesignLiDAR QCGeodetic Control
Feb 2012 – Aug 2013

Interim Engineering Manager | Survey Manager

Andrade Gutiérrez S.A. — Las Placetas Hydroelectric Project ($300M+) · Dominican Republic
  • Promoted to Interim Engineering Manager to lead technical reactivation of a stalled $300M+ hydroelectric project (paralyzed since 2009). Coordinated external design consultant and managed full execution of the Alternative Basic Design: 2 cascade hydro plants (111.32 MW total), 2 CCR dams, 3 pressure tunnels (20.16km combined). Delivered conceptual approval in October 2012 — 6 months from assignment.
Engineering ManagementHydroelectricProject Reactivation
1994 – 2003

Earlier Experience — Survey, Quantities & Design

NCC-OCECON, Consorcio INARSA+TECNOAMERICA, INGCO / Constructora Luz Abréu · Dominican Republic
  • Earthwork volumetrics, payment certifications, and topographic support across multiple highway and dam projects including Guaigüí Dam, Santiago Northern Beltway (8-ramp cloverleaf interchange, 3.75km), and Autopista Duarte Widening (Lots III & IV).
QuantitiesTopographyHighway Design

Technical Competencies

Project Controls & Quantity Surveying

Field Quantity Take-Off & Pay Certification96%
Change Order Evaluation & Documentation94%
WBS Development & Cost Tracking92%
Schedule Integration & Field Progress Tracking90%

Geospatial & Survey

LiDAR Processing & Classification95%
Drone Photogrammetry (Pix4D)93%
TBM Alignment & Geodetic Control96%
Global Mapper / GIS90%

Systems & Automation

Excel VBA (Advanced)97%
AutoCAD API / DDE / COM Integration90%
Engineering Document Control (EPC)95%
Earthwork Estimation & Mass Haul96%

Software & Tools

Design: AutoCAD (Expert, 2D/3D/VBA), Eagle Point (R13/R2010 — production tool), Civil 3D (rapid adaptation)
Geospatial: Global Mapper, Pix4D, Topcon Tools, Machine Control DTM (Trimble/Topcon)
Project Controls: MS Project, cost/schedule tracking, WBS, EPC contractor interface
Programming: Excel VBA (Advanced), AutoCAD API/DDE/COM, Monte Carlo simulation (Newton-Raphson)
Languages: Spanish (native) · English (professional) · Portuguese (professional)

Key Projects

Montegrande Dam — Andrade Gutiérrez ($500M+)

Dominican Republic · Feb 2018 – Dec 2021

Embankment dam with asphalt core (L=2.2km, H=57m). Active EPC environment with multiple concurrent design firms. Resolved payment certification impasse on 12M m³ earthwork between contractor and client.

12M m³Excavation controlled
2,800LiDAR sections automated
$1.6M+Doc control savings
100%Audit compliance
QTOPix4DLiDAR/ICODVisual CRPGeotechnical

Palomino Hydropower — Odebrecht ($400M+)

Dominican Republic · Feb 2006 – Jul 2011

Dominican Republic's largest underground infrastructure project. 12.44km TBM double-shield tunnel, underground powerhouse with 11 interconnected tunnels, 400m surge shaft, 60m CCR dam, 19km transmission line.

12.44kmTBM alignment controlled
9,531Rings installed
80Personnel managed
$708KPay cert delivered
TBMUndergroundSALT SystemQTO / Pay CertsChange Orders

Las Placetas Hydroelectric — Andrade Gutiérrez ($300M+)

Dominican Republic · Feb 2012 – Aug 2013

Reactivation of stalled project. 2 cascade hydro plants (111.32 MW), 2 CCR dams, 3 pressure tunnels (20.16km combined). Promoted to Interim Engineering Manager — delivered conceptual approval in 6 months.

111.32 MWCombined capacity
20.16kmPressure tunnels
6 monthsTo conceptual approval
Engineering ManagementDrone PhotogrammetryHydroelectric

Proprietary Engineering Systems

Four systems deployed across $2B+ in combined EPC project value. Not side projects — production tools validated by external auditors on active megaprojects.

Visual CRP

Engineering Document Control · 21+ Years · visualcrp.com

Manages the operational document control layer that teams perform manually in Excel — transformed into a structured, multi-user system that coexists with contractual platforms (Procore, Aconex, Citadon) without replacing them.

15K+Records managed
60+Daily users
$1.6M+Verified savings
100%Audit compliance
Excel VBADocument ControlEPCProcore Compatible

ICOD

LiDAR Tunnel Cross-Section Automation · 2020

Excel VBA–AutoCAD API application that processes high-density LiDAR point clouds from tunnel laser scanners and automatically generates cross-sections. Developed in 2 weeks when no commercial tool could handle the data complexity.

4,000+Points per section
2,800Sections auto-generated
75%Drafting time reduction
LiDARExcel VBAAutoCAD APITunnel Design

AC&P

Parametric Cost Estimation · Since 2004

Dual-accounting architecture separating cost base from strategic bid price, with inverse factorization engine. Produces 10 automated reports: monthly cash flow, material quantification, labor scheduling, change order support, and bid pricing. Analytical layer complementing HeavyBid, WinEst, Oracle.

Cost EstimationExcel VBACash FlowChange Orders

SALT

Topographic Survey Adjustment · Since 2004

Implements Compass Rule, Crandall Rule, and Transit Rule polygon closure with proportional angular and linear adjustment, GPS integration, CSV coordinate export, and direct AutoCAD drafting output. Used on Palomino ($400M+) for full 12.44km TBM geodetic control network.

1:52,753Precision achieved
16.2kmControl network
GeodesyExcel VBAAutoCADTBM Control

Value to Employers

What a hiring organization gains by bringing this experience to their project controls team — framed around the three areas where my background directly addresses common gaps in EPC project execution.

Independent Quantity Verification — Owner's Representative Capability

On the Montegrande project, the quantity department and the client were at an impasse on 12M m³ of earthwork. I delivered an independent evaluation that unblocked the certification process. That is exactly what an Owner's Representative does on a capital project: verify what the contractor reports, not execute it.

  • Field quantity take-off independent from contractor reporting
  • Payment certification review and validation against field conditions
  • Change order evaluation with alignment log maintenance
  • Experience on both sides — EPC contractor (Odebrecht) and owner/supervision (Andrade Gutiérrez)
Relevant for: Duke Energy, Fluor, and any owner or EPCM firm needing independent QTO and payment cert review on power generation or infrastructure capital projects.

Proprietary Automation That Solves Problems Commercial Software Cannot

ICOD was built in 2 weeks because no commercial tool could process 4,000-point LiDAR cross-sections at tunnel scale. Visual CRP was built because Procore, Aconex, and Citadon do not solve the operational document control problem on fast-track EPC projects — they solve the contractual one. These are not workarounds. They are solutions that external auditors validated alongside the commercial platforms.

  • Excel VBA + AutoCAD API: production-level automation deployed on $500M projects
  • Systems that run alongside Procore/Aconex, not instead of them
  • Ability to build custom tools when standard software hits its limits
  • $1.6M+ in verified savings from document control alone
Relevant for: Any EPC or EPCM environment where project controls teams are managing document workflows in Excel because the enterprise platform does not cover operational needs.

Field-to-Office Integration — Progress Tracking Tied to Schedule

Biweekly drone photogrammetry campaigns over 12M m³ of active excavation, correlated to construction schedule milestones for owner reporting and EPC contractor schedule validation. That is field progress tracking integrated with schedule — not two separate processes.

  • Drone photogrammetry (Pix4D) for volumetric progress measurement
  • Correlation of field data with schedule milestones for owner reporting
  • TBM daily advance tracking: 20 months of continuous records (9,531 rings, 12.44km)
  • Geotechnical program management with real-time data processing
Relevant for: Roles requiring field-side project controls — progress measurement, earned value data collection, and schedule integration on active construction projects.

Quantified Track Record

75%
Reduction in manual process time (ICOD)
$1.6M+
Verified savings — document control
100%
Audit compliance — Visual CRP deployments
$2B+
EPC project value supported
12.44km
TBM alignment maintained within spec
25+
Years EPC megaproject experience

Education & Credentials

Formal Education

B.S. Civil Engineering

Universidad Tecnológica del Cibao (UTECI), La Vega

1999

A.S. Information Technology

Universidad Nacional Pedro Henríquez Ureña (UNPHU), La Vega

1992

Credentials & Recognition

Professional Engineer License — CODIA #17378

Colegio Dominicano de Ingenieros, Arquitectos y Agrimensores · Active since 2001

Engineering Exchange Program — UAEM México (1998)

Conference: "Facilities Offered by Computer Use in Highway Design"

Roadcalc Training Instructor

10 courses · 100+ engineers trained

Technical Publications

Technical-Financial Risk Report — Santo Domingo Metro Line 3 (2026)

Independent professional analysis establishing a methodological framework for ex-ante evaluations on mass transit projects. Documents methodology, operational capacity findings, design gaps, and projected financial risk.

View full publication

Case Study: Visual CRP Implementation at Montegrande Dam

Documented implementation serving as reference for hybrid document control architecture in EPC megaprojects. Includes audit validation results and cost savings methodology.

Explore case study

"The ex-ante evaluation methodology presented by Engineer Bonilla establishes a new standard for technical analysis in the design phase. It stands out for its capacity to integrate analysis of existing studies, comparative evaluation of international challenges, and rigorous study of applicable technologies, articulated through advanced technical-financial modeling."

— Ing. Carlos Sully Bonnelly Ginebra, PhD | International Consultant in PPP & Transport Economics | Faculty